Assign the people and resources before committing.
| Proposed role | Responsibility | Current status |
|---|
| Buyer design owner | Approves requirements, interface, drawings and final acceptance. | Named assignee, availability and authority not yet confirmed. |
|---|
| Project coordinator | Tracks scope, English technical communication, quote inputs and decisions. | Named assignee, availability and authority not yet confirmed. |
|---|
| Integration / controls engineer | Owns the permitted electrical/software interface and test configuration. | Named assignee, availability and authority not yet confirmed. |
|---|
| Mechanical / manufacturing engineer | Owns DFM, process selection, material and inspection plan. | Named assignee, availability and authority not yet confirmed. |
|---|
| Validation / configuration engineer | Owns measurements, calibration references, evidence and issue tracking. | Named assignee, availability and authority not yet confirmed. |
|---|
The four delivery roles are a planning model for the current delivery team; assignments, equipment and capacity have not been verified. Historical original-supplier work is not automatically attributed to that team.
Alliance identity: Jaia Robotics — unknown; 合機 (Hé Jī) succession/core team and Jing Mao manufacturing coordination — user-confirmed. This work package: research proposal, no confirmed engagement. Legal supplier, subcontractors and acceptance signatory remain to be designated.
NOT EXECUTED / PROPOSED TEST PLAN
Every stage has an entry and an exit.
Numeric limits are agreed with the buyer before testing. An unspecified limit blocks acceptance. Each run must record hardware, firmware, OS, software/model, test configuration, environment, workload and operator; mark irrelevant fields N/A with a reason.
| Stage | Entry condition | Method | Pass / exit condition | Evidence files |
|---|
| Desktop / interface review | Buyer supplies versioned documents and an authorised interface owner. | Trace each required signal from sensor output to host input. Check units, timing, licences and power limits. | Each required field has an agreed value or explicit blocker; both interface owners approve the revision. | interface-contract.csv; questions.csv |
|---|
| Offline / sample replay | A permitted sample file and agreed schema exist; no vehicle commands enabled. | Replay the same sample twice; add a duplicate, missing timestamp and out-of-range value. Compare accepted/rejected records. | All deliberately invalid records are flagged; deterministic output; no silent duplicate. This verifies the parser only. | replay-log.jsonl; manifest.csv |
|---|
| Ground bench / sensor | Hardware, calibrated reference, safe power supply, owner and thresholds approved. | Compare the sensor with the reference at buyer-agreed points. Interrupt and restore data transfer; reconcile record IDs. | Calibration error, timing and recovery meet signed thresholds; gaps are reported and configurations match. | measurement.csv; calibration-reference; recovery-log |
|---|
| Controlled water test | Approved wet-test procedure, equipment, location and responsible operator available. | Test agreed sealing/exposure and repeat acquisition under the specified environment; inspect before/after. | No unrecorded failure; all environmental and data limits in the signed plan met. Passing a bench does not pass this gate. | environment-log; inspection-report; acceptance-signoff |
|---|
All stages are currently unexecuted. Simulation/replay verifies only the named software behaviour. Bench, environmental and field results remain separate. Stop if a prerequisite, permit, safe test arrangement or accountable operator is missing.
Cross-cutting configuration and supply-chain record
Record voltage, continuous/peak power, mass, cooling, mounting, connector pinout, protocol, units, frequency, time source, latency, memory/storage, offline/loss-of-link behaviour, authentication, permissions, update/rollback, logs, HBOM/SBOM and code/model/data licences. Confirm who can read, store, receive, update or control data; offline operation; and where post-processing happens.
Unknown / blocking: Sensor and vehicle SKU; wet connector; pressure/saltwater scope; software/API access; current equipment; licences; named technical owner; quantity, budget and schedule. No values are inferred from historical flight or water-quality accounts.
These are working templates created for this proposal, not completed measurement records or inspection reports.